South West Growth Area

Austral & Leppington Wastewater Servicing 

Building Wastewater Services in Austral
To service about 3,100 homes in the Austral Precinct, we have started construction on new wastewater infrastructure.

This includes:

  • A wastewater pumping station
  • 6.2km of trunk wastewater infrastructure

This work is expected to be complete in mid-2016.

Source: Sydney Water South West Growth Areas - Community Update February 2016

Western Sydney Infrastructure Plan: 

Background

Western Sydney Infrastructure Plan:
The $3.5 billion commitment for the Western Sydney Infrastructure Plan includes:
• Bringelly Road—upgrade to four lanes from Camden Valley Way to the Northern Road (10km, $500 million)
• The Northern Road—upgrade to a minimum of four lanes from Narellan to M4 Motorway (31km, $1.6 billion)
• Elizabeth Drive Corridor—construction of a new four lane motorway between the M7 Motorway and The Northern Road (14km, $1.25 billion)
• Improve interchanges connecting The Northern Road and the new motorway with arterial roads
• Local roads package—$200 million for local road upgrades

Source: Western Sydney Infrastructure Plan